Construction Management of Randselva bridge - Assessment between two construction methods: cantilever concrete and steel-box method.
Abstract
Purpose of the master thesis is to perform a construction and cost analysis of two proposedsolutions for the Randselva bridge on E16 roadway. Project data is based on information datagiven from Statens Vegvesen , Trondheim along with MultiConsult construction company.Information data consist of all aspects of construction: from geotechnical surveys andgeological inspections to final construction solutions with drawings, stated in further tables of contents.Construction analysis will be performed as static system analysis with given cross-sectionsand materials, without designing the sections. Optimization process will be performed inorder to update the further cost estimates. All calculation data will be processed and analyzed in software SoFiSTiK AG .Profitability and cost analysis will consist of uncertainty analysis in the Projection method along with the Successive calculation method . Both methods are popular in projectmanagement and financial analysis of construction enterprises and are based on risk factorsand uncertainties values used in cost estimation. The analysis will be performed for bothconcrete and steel solutions. Results will be presented in tables and charts.All data will be then analyzed in the computer program ANSLAG provided by thesupervisor and NTNU University. Computer analysis will conclude in final uncertaintyprojection and cost estimations for both construction solutions. Report will conclude then onresults comparison with adequate comments.