Utslippsfrie bygge- og anleggsplasser

Lüthe, Henrik Moen; Klævold, Kari Sværen; Botn, Mathias Oliver; Edvardsen, Øyvind Andreas
Bachelor thesis
Thumbnail
View/Open
no.ntnu:inspera:108215446:111553772.pdf (27.28Mb)
URI
https://hdl.handle.net/11250/3005578
Date
2022
Metadata
Show full item record
Collections
  • Institutt for elkraftteknikk [2666]
Abstract
Bygge- og anleggsbransjen står for store nasjonale klimagassutslipp. Norge har forpliktet

seg utover parisavtalen til å redusere utslippene med 50-55%, sammenlignet med nivåene

i 1990. For å nå disse målene må utslippene kuttes, og fremtidens bygge- og

anleggsplasser må bli utslippsfrie. Flere norske storbyer har skrevet under på en felles

storbyerklæring, hvor de går sammen om at kommunenes bygge- og anleggsprosjekter

skal være utslippsfrie innen 2025.

Norconsult er rådgivere i alle ledd av plan- og byggefasen, og har et ønske om å heve sitt

kompetansenivå på dette området. Denne rapporten skal undersøke hvordan en kan

gjennomføre et bygge- og anleggsprosjekt utslippsfritt, samt peke på hvilke utfordringer

som oppstår og hvilke løsninger som finnes. Gjennom intervjuer av blant annet

byggherrer, entreprenører, nettselskaper og maskinleverandører samles erfaringer og

synspunkter fra de forskjellige partene.

Utslippsfrie bygge- og anleggsplasser skaper nye utfordringer. Markedet for utslippsfrie

anleggsmaskiner er for øyeblikket lite, og består i stor grad av elektriske anleggsmaskiner

som har et høyt effektbehov. Dette skaper utfordringer med å få levert nok effekt fra

strømnettet. I tillegg er det knyttet store investeringskostnader til innkjøp av

utslippsfrie anleggsmaskiner.

Gjennom undersøkelser og intervjuer ble det konkludert med at det er mulig å

gjennomføre bygge- og anleggsplasser utslippsfritt. Elektriske anleggsmaskiner vil spille

en stor rolle, og planlegging av strømtilførselen til maskinene bør gjøres så tidlig som

mulig. For å gjennomføre et prosjekt utslippsfritt, kreves det tydelige krav i

anbudsdokumenter fra byggeherre. Alle partene må involveres tidlig i planleggingsfasen,

og samarbeid mellom dem er en forutsetning for å gjennomføre et slikt prosjekt.
 
The construction industry is responsible for a subststantial amount of greenhouse gas

emissions. Norway has made an obligation exceeding the Paris Agreement to reduce the

emissions by 50-55 % compared to the levels in 1990. To reach these goals, the emissions

must be reduced, and the construction sites of the future must be completely emission

free. A great deal of Norwegian cities have united and signed a declaration, stating that

the construction cites in the municipalities will be emission free within 2025. The

declaration is called "Storbyerklæringen".

Norconsult is an advisor in every aspect of the plan- and contruction phase and have

ambitions to increase their level of knowledge in the field. This report will examine how

a construction site can be carried out completely emission free, while pinpointing the

challenges that might occur, as well as the solutions that will be unveiled. By

conducting interviews of contractors, power companies, mobile battery suppliers and

machine producers the group has gathered experiences and perspectives from the trade.

Zero emission construcion sites creates new challenges. The market for zero emission

heavy machines is limited at the moment, and consist largely of electrical machines with

high power requirements. This creates challenges for the electrical grid to deliver enough

power to the construction sites. In addition to this, there is a considerable cost of

investment attached to acquiring new zero emission machines.

It was concluded through thorough studies and interviews that it is possible for a

construction site to be emission free. Electrical machines will play an important part,

and the planning of the power supply for the machines must be conducted at an early

stage in the engineering process. For a project to be carried out emission free, there has

to be distinct demands in the tender document carried out by the construction client.

All parts must be involved early in the planning phase, and the cooperation between

them is a prerequisite for a project like this to be carried out.
 
Publisher
NTNU

Contact Us | Send Feedback

Privacy policy
DSpace software copyright © 2002-2019  DuraSpace

Service from  Unit
 

 

Browse

ArchiveCommunities & CollectionsBy Issue DateAuthorsTitlesSubjectsDocument TypesJournalsThis CollectionBy Issue DateAuthorsTitlesSubjectsDocument TypesJournals

My Account

Login

Statistics

View Usage Statistics

Contact Us | Send Feedback

Privacy policy
DSpace software copyright © 2002-2019  DuraSpace

Service from  Unit