Vis enkel innførsel

dc.contributor.advisorLau, Albert
dc.contributor.advisorBruland, Amund
dc.contributor.authorMoe, Britt Karin
dc.date.accessioned2021-10-03T16:42:06Z
dc.date.available2021-10-03T16:42:06Z
dc.date.issued2021
dc.identifierno.ntnu:inspera:80614265:15939521
dc.identifier.urihttps://hdl.handle.net/11250/2787276
dc.description.abstractDet har vært en økning i tverrsnittsstørrelsene til jernbanetunneler i tråd med den teknologiske utviklingen, fra de første togene begynte å kjøre på skinner i Norge. Økningen i tverrsnittsstørrelsen kan forsvares med økt- og endret plassbehov i tunneltverrsnittene, men det har vist seg å finnes svært lite litteratur og dokumentasjon knyttet til prosjektering av tverrsnittsstørrelsen til jernbanetunneler. Det er funnet at det for enkelte nyere prosjekter er prosjektert med større tverrsnittsstørrelse for tunnelene enn det som er anbefalt i standarden. Derfor ble det funnet nødvendig å undersøke hvor store tunneltverrsnittene behøver å være. I prosjektet ble det foretatt målinger av tunneltverrsnittet på to tunneler på Gardermobanen, som videre ble modellert og analysert med tanke på å undersøke om det var mulig å redusere tverrsnittsstørrelsene. Disse tunneltverrsnittene ble videre sammenlignet med tunneltverrsnitt fra nyere prosjekter, for å undersøke potensialet for tverrsnittsreduksjon i henhold til dagens standard. Videre ble en beregningsmodell for kostnader og CO2-utslipp fra byggefasen etablert, for å undersøke hvilken effekt tverrsnittsreduksjon hadde på kostnader og CO2-utslipp fra byggefasen, og hvor data fra analysen av tverrsnitt ble anvendt som inngangsparametere. Det ble funnet at sonen for evakuering, sonen for faste installasjoner og sporkonstruksjonen var områdene i tunneltverrsnittet med mest potensiale for reduksjon. Reduksjonspotensialet til evakuerings- og rømningssonen kom fra muligheten til å kombinere disse til en sone. Det ble videre funnet at ballastfritt spor som sporkonstruksjon gir et slankere tunneltverrsnitt. Ved å gjennomføre reduksjon på disse områdene ble det funnet et reduksjonspotensiale for tunneltverrsnittene i størrelsesorden 10m2. Dette gir følgelig en reduksjon av drivekostnader i størrelsesorden 4000 kr/m, reduksjon i CO2-utslipp på 500 kg CO2 pr enhetslengde og en reduksjon i avgifter knyttet til CO2-utslipp på 900 kr pr enhetslengde. Gjennom prosjektet ble det funnet at dagens prosjekteringsmetoder i liten grad er egnet for optimalisering av tunneltverrsnitt, i lys av hvor stort reduksjonspotensiale som ble avdekket i prosjektet, i tillegg til flere faktorer knyttet til kompleksiteten av jernbanetunneler, som gjør prosjektering utfordrende.
dc.description.abstractThere has been an increase in the cross section size of railway tunnels in line with the technological development the past 100 years, from when the first trains started to run on rails in Norway. The increase in the cross section size can be explained by increased- and changed space requirements in the tunnel cross section, but it has been limited literature and documentation on the subject of design and engineering of railway tunnels. It was shown from some newer projects, that the projects have designed the cross section larger than the requirements of the technical standards. Therefore it has been found necessary to investigate how big the cross section of railway tunnels are required to be. Measurements of the cross section size of two tunnels on the Gardermoen-line was obtained, which were further modelled and analysed in regards to investigating if it were possible to reduce the cross sections. These cross sections were further compared with cross sections from newer projects to investigate the reduction potential in relation to today’s technical standards. A simplified computational model for cost and CO2-emission from the building phase was established to investigate the effect of cross section reduction on the cost and CO2-emissions, where the data from the analysis of the cross sections were used as input parameters. It was found that the area for evacuation, fixed installations and the track construction were the areas within the cross sections with the highest reduction potential. The reduction potential for the evacuation- and the installation area came from the possibility of combining the areas. It was further found that ballast-less track as the track structure can result in a smaller cross section. By conducting a reduction in these areas, it was found that the reduction potential for the cross sections was in the magnitude of 10m2. This gave a reduction in the construction cost in the magnitude of 4000 NOK/m, a reduction in the CO2-emissions of 500 kg CO2 pr unit length, and a reduction in the costs related to the CO2-emissions of 900 NOK pr unit length. Through the project, it was found that today’s designing method in little degree is suitable for optimization of tunnel cross section size, in light of the great reduction potential found in the project. In addition to this, several factors related to the complexity of railway tunnels also makes the design process challenging.
dc.languagenob
dc.publisherNTNU
dc.titleMulighetsstudie av reduksjon av tverrsnittsstørrelsen til jernbanetunneler med hensyn på kostnader og miljø
dc.typeMaster thesis


Tilhørende fil(er)

Thumbnail

Denne innførselen finnes i følgende samling(er)

Vis enkel innførsel